Project Overview

36” Paradise Power Plant Raw Water Intake, Drakesboro, KY

Work included the installation of 345 feet of 36 inch steel pipe with an underwater recovery for a raw water intake at the new Paradise Combined Power Plant.  Ground conditions consisted of Clay, silty clay with some sand.  The MTBM was launched out of a 20 foot diameter caisson and recovered in the river with a barge mounted crane and divers.

Location

Drakesboro, KY

Owner

Tennessee Valley Authority

Date

Spring 2016